CNC Machining Cost & Quote Calculator

Enter quantity, machining minutes, blank cost, preparation time and your shop rate. Dimvo separates material, run time and preparation, then calculates total cost, target selling price and price per part.

Method
machining-quote
Version
1.0.0
Checked
Known answers + invalid inputs · 6 Aug 2026

Decimal points and decimal commas are accepted.

Illustrative example. Replace every rate and cost with your own shop values.

Part and batchyour shop values

Rough quote · ex VAT

Suggested batch price
€400.00
Selling price / part
€40.00
Estimated batch cost
€320.00
Cost / part
€32.00
Gross profit
€80.00
Actual gross margin
20%
Material
€80.00
Machining
€150.00
Preparation
€90.00

Rough shop estimate, not a binding quotation. Tooling, scrap, inspection, subcontracting, packing and VAT are not included in this quick estimate.

Quick use

How to use this calculator

  1. Enter quantity, blank cost and machine minutes per part.
  2. Enter the all-in shop rate and one-time preparation time.
  3. Choose target margin and review the full cost breakdown before adding omitted risks or services.

Method

Equation

Cost = material + run time + preparationPrice = cost / (1 − target margin)

Limits

Assumptions

  • All monetary inputs are user supplied
  • Shop rate is all-in
  • VAT, scrap, tooling and inspection excluded in quick mode

Provenance

Independent calculation

Generated from the displayed equation and user inputs. This page does not reproduce a standard or third-party table.

Common questions

Frequently asked questions

How is CNC machining cost calculated?

The quick model adds material cost, machine time at the shop rate and one-time preparation cost. Selling price is cost divided by one minus the target margin.

Are margin and markup the same?

No. Margin is profit divided by selling price; markup is profit divided by cost. Dimvo asks for target margin and shows the resulting price.

What should a formal machine-shop quote add?

Add tooling, scrap risk, inspection, programming, finishing, subcontract work, packaging, transport, VAT and commercial conditions where applicable.